Received notification from the datacenter staff that this week they will have a time set for replacement of the power distribution unit. My guess is that it will probably be replaced within the next 7 to 10 days.
As long as the PDU is the only issue, this should resolve the server power disruption problems and resulting site downtime it has been causing.
If the sporadic reboots continue after the PDU replacement then that will mean it is very likely to be a hardware issue with the server and a bit more work to be done to sort this all out.